Candeur Eternia Construction Update
June 2026 – Latest Progress

Floors 16–30 actively under construction. Foundation to podium complete. Possession targeted 2027. Updated monthly.

Construction Timeline

Q3 2023 ✓ COMPLETED

Foundation Work

Foundation and basement construction completed for all 4 towers. Basements in RCC designed to withstand wind and seismic loads.

Q1 2024 ✓ COMPLETED

Podium Structure

Podium level parking structure and ground-floor structural work completed for all towers. Multi-level basement parking framework established with ramp access.

Q3 2024 ✓ COMPLETED

Tower A & B – Floors 1–15

Structural work completed up to the 15th floor for Tower A and Tower B. RCC monolithic shear wall construction visible. Lifts and service shafts in place.

Q2 2025 – Q2 2026 🔨 IN PROGRESS

All Towers A, B, C, D – Floors 16–30

Structural work currently active across all four towers from floor 16 upward. External façade work commencing on lower floors. Slab casting and column construction at upper levels ongoing. This is the most visible phase of construction from the road.

Q3–Q4 2026 UPCOMING

Interior Finishing

Tiling, plumbing, electrical wiring, door frames, and internal finishing work to commence once structural work is complete. Clubhouse interior construction also in this phase.

2027 UPCOMING

Possession

Targeted possession for all towers. This is the RERA registered completion date. Buyers will receive OC (Occupancy Certificate), handover kits, and possession letters.

How to Track RERA Progress Independently

Candeur Eternia is RERA registered under number P02200010709 in Telangana. You can verify construction progress, possession dates, and developer compliance directly on the RERA portal.

  1. Visit rera.telangana.gov.in
  2. Click on "Project Search" or "Registered Projects"
  3. Enter RERA number P02200010709
  4. View project details, developer submissions, and quarterly progress reports
  5. Check the possession date filed with RERA vs. developer's stated timeline

💡 RERA mandates that developers file quarterly construction updates. If a developer fails to file or misses deadlines, buyers can file complaints directly through the RERA portal.

Construction Quality Highlights

  • 🏗️ RCC Monolithic Shear Wall Construction: Superior seismic resistance compared to conventional column-beam structures. Fewer interior columns means cleaner, more spacious interiors.
  • 🪟 UPVC Windows and Balcony Doors: UPVC fixed / casement windows and sliding balcony doors with single glazed glass and provision for fly mesh.
  • 🧱 Solid / AAC Block Work: Block work with solid or AAC blocks in the designated areas.
  • 🚿 Reputed-Make Fittings: Reputed make sanitary fixtures and CP fittings in the toilets.
  • 🏠 Vitrified Tile Flooring: Vitrified tiles of reputed make in living, bedrooms, kitchen and balconies.
  • 🍳 Kitchen Provisions: No kitchen counters are provided. Sink plumbing and electrical provisions for RO, hob, chimney, refrigerator, microwave/oven and mixer/grinder are given.
  • 🔌 Power Backup & EV: 100% DG backup with auto change-over (excluding EV charging), with a provision for common EV charging stations in Basement-1.

Developer: Candeur Constructions

Candeur Constructions has a clean track record in Hyderabad real estate. Their previous projects — Candeur Landmark in Manikonda and Candeur Serene in Gachibowli — were delivered on time with OC obtained. The developer has consistently maintained RERA compliance across all registered projects.

For Candeur Eternia specifically, the pace of construction — from foundation in Q3 2023 to floors 16–30 active as of mid-2026 — is consistent with the stated 2027 possession timeline. This is a project where the physical reality of construction matches the paperwork.

As always, we recommend buyers independently verify RERA status at rera.telangana.gov.in before finalising any purchase decision.

📸

Latest Construction Photos & Video

For the latest site photos and video walkthroughs, WhatsApp us. We visit the site regularly and can share current ground-level updates.

📸 Get Construction Photos Book Site Visit →

Disclaimer

The content is for information purposes only and does not constitute an offer to avail of any service. Prices mentioned are subject to change without notice and properties mentioned are subject to availability. Images for representation purposes only.

This is the official website of authorized marketing partner. We may share data with RERA registered brokers/companies for further processing. We may also send updates to the mobile number/email id registered with us. All Rights Reserved.